NT,



Just wondering how to change the contract months within NT. The reason I'm asking is I'm running a trial version of NT from Spike along with a trail version of SR.

Today is March the 10, thus time to flip over to the June contracts but when I look at the market depth within NT today the ladder and price is showing the March prices not the June prices. How do you update the securities to the June prices?

UnderGround

NinjaTrader_Vincent
03-10-2005, 04:33 AM
Hi Underground,

Go to the Instrument Manager under Tools in the NinjaTrader Control Center. Select the March contract in the left window, change the expire date from March into June and press add. The June contract should now be in the left window of the Instrument Manager as well as the Instrument section of the SuperDOM

Vincent